Major Repairs of Tuyere Zone and Shaft Lining of Blast Furnace # 5 for “NLMK”, JPSC
On October 17, 2025, we started on the repairs to the refractory lining of Blast Furnace # 5 at “NLMK”, PJSC. As of today, shotcreting has been completed on the eighth and ninth rows of coolers and the uncooled zone of the shaft’s working layer.
24 October 2025
24 October 2025
Complete Overhaul Of Blast Furnice № 10 of “MMK”, PJSC, Shaft Lining
From Sept 20,2025 to Sept 30, 2025, our company completed overhaul of BF No. 10 shaft lining. The project envisaged shotcreting of the working layer of the shaft from +14.100 to +35.645, as well as injection of refractory concrete into the furnace casing.
25 September 2025
25 September 2025
Refractory Shaft Lining of Blast Furnace No. 2 of “Tulachermet”, PJSC
From Sept 11, 2025 to Sept 28, 2025, our company made a restoration repair of refractory lining of the furnace and shaft of the blast furnace No. 2 for “Tulachermet”, PJSC.
16 September 2025
16 September 2025
“Severstal”, PJSC, Completion of Work on Technical Re-Equipment of Heating Furnace № 3
On Sept 5, 2025, at 21:00, the ignition of heating furnace № 3 LPC-2 of “Severstal”, PJSC, took place. Drying and heating is to be carried out according to the previously approved schedule designed for 12 days. As for now, the temperature in the furnace is 350 ° C. Putting slabs into the furnace and reaching operating parameters is scheduled for September 18, 2025.
16 September 2025
16 September 2025
«Severstal» PJSC, Technical Re-Equipment of Heating Furnace No. 3
«Refracon Installations», LLC, is participating in a large-scale project for the technical re-equipment of heating furnace No. 3 of «Severstal» PJSC, Cherepovets.
21 August 2025
21 August 2025
Robotized Repair of Lining of Blast Furnace No. 1 of EVRAZ ZSMK, JSC
In June 2025, our company’s specialists carried out a project on robotized repair of Blast Furnace No 1 of “EVRAZ ZSMK”, JSC, using shotcrete process amid complete overhaul of the III category.
2 July 2025
2 July 2025
JSC “EVRAZ ZSMK”. Repair of Air Heater No. 1 of Blast Furnace No. 1
In April 2025 we successfully completed the project to restore the damaged section of the lining of the combustion chamber of hot air heater No.1 of blast furnace No.1 of the blast furnace shop of JSC EVRAZ ZSMK.
14 April 2025
14 April 2025
Repair of Air Heater № 1bis of Blast Furnace № 1 of “ChMK”, PJSC
In September 2024, “Refracon Installations”, LLC, specialists restored and repaired the combustion chamber of air heater No. 1bis of Furnace № 1 of “ChMK”, PJSC.
7 October 2024
7 October 2024
Shotcreting of Steel Ladles for NLMK, PJSC
Shotcreting is an installation technology that combines the use of high—density refractory casting material with low or ultra-low cement content and pneumatic spraying technology.
7 October 2024
7 October 2024
Overhaul of the Shaft Lining of Blast Furnace # 8 of MMK, PJSC
In mid-March 2024, our company completed a major overhaul of the blast furnace shaft #8 of MMK, PJSC, consisting of two stages
29 March 2024
29 March 2024