Restoring repair of the refractory lining of “Tulachermet”, PJSC, BF #3 air heater combustion chamber.

In mid-April 2023, our company completed the project for the restoring repair of the refractory lining of Blast Furnace # 3 of “Tulachermet”, PJSC.
12 May 2023

Overhaul of shaft lining of blast furnace #4 for “Magnitogorsk Iron and Steel Works”, PJSC

We repaired the shaft lining of blast furnace #4 for “Magnitogorsk Iron and Steel Works”, PJSC, from December 2022 to April 2023. The process consisted of two stages
13 April 2023

Repair work of BF №8 of «MMK», PJSC, with a robot set

In December 2022, the repairs of the top two rows of cooling plates and the uncooled part of the stack of blast furnace # 8 of Magnitogorsk Iron and Steel Works were completed.
9 January 2023

Refurbishment of the refractory lining of BF # 3 of PJSC “Tulachermet”

In early November 2022 we completed the refurbishment project of refractory lining of Blast Furnace #3 of Tulachermet, PJSC.
5 December 2022

Installation of monolithic lining of Blast Furnace #1 of PJSC ChMK

In September 2022 we completed the installation of a monolithic shaft lining, armor and dome plate, and protection of gas duct mouths of blast furnace #1 of Chelyabinsk Iron and Steel Works.
10 October 2022

First Category Total Overhaul of Blast Furnice # 10 of MMK, PJSC, shaft lining.

At the end of June 2022, Refracon Installations completed blast furnace # 10 shaft lining overhaul at Magnitogorsk Iron and Steel Plant.
7 July 2022

The Second Stage of the Overhaul of BF No. 9 “MMK”, PJSC, Lining.

In May 2022, our company completed a major overhaul of shaft BF No. 9 of MMK, PJSC, consisting of two stages
6 June 2022

OVERHAUL OF AIR HEATER № 10 OF BLAST FURNACE № 4 OF “CHMK”, PJSC

In April 2022, “Refracon Installations”, LLC, specialists carried out a complete renovation of the air heater combuster № 10 of DP4 of “ChMK”, PJSC, using a shotcreting method.
27 May 2022

Stage One of Overhaul of BF No. 9 of PJSC MMK Shaft Lining.

By April 2022, the first stage of the project was completed, under which 192 refrigeration plates were lined. The work scope included: welding of anchors, installation of formwork, pour of concrete by vibrocasting application, and drying.
19 April 2022
ДП-2 ПАО «ТулаЧерМет».

Reсonstruction of the hearth and stack of Blast Furnace-2 at TulaCherMet PJSC.

In late October of 2021 specialists of Refracon Installations Ltd. completed the reconstruction of refractory lining of BF No.2 at TulaCherMet PJSC.
17 December 2021