Rus +7 (4742) 24-30-21

News

Major Overhaul of Blast Furnice #4 of «NLMK», PJSC

June 2026 saw the first stage of the project completed, during which 108 cooling plates werepoured with concrete. The scope of work included: welding of anchors, installation of formwork,concrete placement using the vibration pouring method, and drying.
10 August 2026

Robotic Repair of Blast Furnace Lining No. 3 for EVRAZ ZSMK, JSC

June 30, 2026 saw the completion of Blast Furnace No. 3 of EVRAZ ZSMK, JSC, repair with a robotic unit. The work was carried out in two stages: firstly, the inner surface of the furnace shaft was washed, then the refractory lining was applied in the area of the cooled zone from+20.763 to+36.674 m, with a smooth change in the thickness of the applied layer from 150 to 500 mm.
3 July 2026

Overhaul Repairs  of NLMK’s Air Heater No. 15

Between May 12 and May 27, 2026, “Refracon Installations”, LLC, specialists repaired the air heater combustion chamber using shotcrete practice
4 June 2026

Repair of Air Heaters № 28 and № 32 of Magnitogorsk MK


8 May 2026

NLMK’s Air Heater № 10 Overhaul Completion.

Air heater refractory lining repair by shotcreting includes dismantling of the destroyed layer remaining bricks and a subsequent complete restoration of the combustor refractory lining.
25 December 2025

“NLMK”, PJSC, Air Heater № 10 Repair

On December 4, we started restoration work on the refractory lining of Air Heater No. 10 combuster of Blast Furnace Shop No. 1 Blast Furnice №3, for “NLMK”, PJSC. Anchors are currently being installed, and relining is being carried out by guniting, with an estimated volume of 165 tons of material.
18 December 2025

Repair of Air Heater No. 11 of Blast Furnace No. 3, for “EVRAZ ZSMK”, JSC

December 8, 2025, “Refracon Installations”, LLC, specialists completed restoration of the refractory lining of Air Heater No. 11 of Blast Furnace No. 3 of the Blast Furnace Shop combustion chamber for “EVRAZ ZSMK”.
18 December 2025

“EVRAZ ZSMK”, JSC, Blast Heater № 11 of BF № 3 Repair

At the end of November 2025, we took on a project to restore BF № 3 blast heater № 11 combustion chamber refractory lining, for “EVRAZ ZSMK”, JSC, Blast Furnace Shop.
2 December 2025

Completion of Total Overhaul of BF No. 5 Lining for NLMK, PJSC,

On October 31, 2025, repairs of the refractory lining of the tuyere zone and the shaft of NLMK’s blast furnace No. 5 were completed.
18 November 2025

Testing New Technology for Pouring Ladles Refractory Lining for “Severstal”, PJSC

In cooperation with “Seven Refractories”, LLC, a new technology for applying materials using a robotic installation has been developed and applied.
18 November 2025