Rus +7 (4742) 24-30-21Kz +7 (7213) 99-61-42

News

Repair work of BF №8 of «MMK», PJSC, with a robot set

In December 2022, the repairs of the top two rows of cooling plates and the uncooled part of the stack of blast furnace # 8 of Magnitogorsk Iron and Steel Works were completed.
9 January 2023

Refurbishment of the refractory lining of BF # 3 of PJSC “Tulachermet”

In early November 2022 we completed the refurbishment project of refractory lining of Blast Furnace #3 of Tulachermet, PJSC.
5 December 2022

Installation of monolithic lining of Blast Furnace #1 of PJSC ChMK

In September 2022 we completed the installation of a monolithic shaft lining, armor and dome plate, and protection of gas duct mouths of blast furnace #1 of Chelyabinsk Iron and Steel Works.
10 October 2022

First Category Total Overhaul of Blast Furnice # 10 of MMK, PJSC, shaft lining.

At the end of June 2022, Refracon Installations completed blast furnace # 10 shaft lining overhaul at Magnitogorsk Iron and Steel Plant.
7 July 2022

The Second Stage of the Overhaul of BF No. 9 “MMK”, PJSC, Lining.

In May 2022, our company completed a major overhaul of shaft BF No. 9 of MMK, PJSC, consisting of two stages
6 June 2022

OVERHAUL OF AIR HEATER № 10 OF BLAST FURNACE № 4 OF “CHMK”, PJSC

In April 2022, “Refracon Installations”, LLC, specialists carried out a complete renovation of the air heater combuster № 10 of DP4 of “ChMK”, PJSC, using a shotcreting method.
27 May 2022

Stage One of Overhaul of BF No. 9 of PJSC MMK Shaft Lining.

By April 2022, the first stage of the project was completed, under which 192 refrigeration plates were lined. The work scope included: welding of anchors, installation of formwork, pour of concrete by vibrocasting application, and drying.
19 April 2022
ДП-2 ПАО «ТулаЧерМет».

Reсonstruction of the hearth and stack of Blast Furnace-2 at TulaCherMet PJSC.

In late October of 2021 specialists of Refracon Installations Ltd. completed the reconstruction of refractory lining of BF No.2 at TulaCherMet PJSC.
17 December 2021

Air heater Nr.11 repair at Blast Furnace 4 at Chelyabinsk Metallurgical Plant

In September 2021 Refracon Installations LLC performed a lining refractory repair of the air heater combustion chamber No.11 of BF No.4 at the Chelyabinsk Metallurgical Plant, using the gunning method.
15 October 2021
ЧМК2

Repair of air heaters No.1bis and No.2 of Blast Furnace No.1 at Chelyabinsk Metallurgical Plant (ChMK)

In May 2021 Refracon Installations LLC completed a new project of refractory lining in which the air heaters’ combustion chamber of Blast Furnace No.1 at ChMK was repaired by shotcreting.
6 July 2021