Rus +7 (4742) 24-30-21Kz +7 (7213) 99-61-42

News

Air heater Nr.11 repair at Blast Furnace 4 at Chelyabinsk Metallurgical Plant

In September 2021 Refracon Installations LLC performed a lining refractory repair of the air heater combustion chamber No.11 of BF No.4 at the Chelyabinsk Metallurgical Plant, using the gunning method.
15 October 2021
ЧМК2

Repair of air heaters No.1bis and No.2 of Blast Furnace No.1 at Chelyabinsk Metallurgical Plant (ChMK)

In May 2021 Refracon Installations LLC completed a new project of refractory lining in which the air heaters’ combustion chamber of Blast Furnace No.1 at ChMK was repaired by shotcreting.
6 July 2021

Lining repair of BF5 at PAO «Severstal» (Cherepovets, Russia)

In late April 2021 Refracon carried out the lining repair of the stack of BF 5 at Cherepovets Metallurgical Plant PAO “Severstal”.
19 May 2021

Rotary Kiln Repair at LafargeHolcim Cement Plant

In February 2021, Refracon took part in the repair of a rotary kiln at the LafargeHolcim Cement plant, located in Ferzikovo village of Kaluga Region.
14 March 2021

Repair of the Air Heater of Blast Furnace No. 10 at Magnitogorsk Iron and Steel Works.

In the second half of December 2020, Refracon Installations LLC performed the restoration of the damaged refractory layer of the combustion chamber for the air heater No. 34 of blast furnace No. 10 at PJSC MMK.
20 January 2021

Gunning installation of refractory lining of beams and columns of BF-4 PJSC «NLMK»

Between November and mid-December 2020 Refracon completed the gunning installation of refractory lining of beams and columns of BF-4 at Novolipetsk Metallurgical Plant.
4 January 2021

Hot reconstructive repair BF-9 of PJSC „MMK“ using robotic shotcreting technology

In early December 2020 Refracon completed the repair of blast furnace No.9 of PJSC „MMK“. During this project, the selected refractory materials were installed using modern robotic shotcreting technology.
17 December 2020

Refractory lining installation of BF-1 PJSC Tulachermet

Refractory lining project of Blast Furnace No.1 of PJSC Tulachermet was completed at the end of September 2020. During this project Refracon performed the following steps: installation of the anchors, preparation of moulds, and refractory installation with shotcreting technique.
15 October 2020

Modernization of the annular heating furnace No. 1 of the pipe rolling shop No. 1 of PJSC “Seversky Pipe Plant”

In July 2020, Refracon took part in the project of modernization of the annular heating furnace No. 1 of the pipe-rolling shop No. 1 of PJSC Seversky Pipe Plant.
24 September 2020

Refracon completed repair of blast furnace No. 6 of EVRAZ NTMK

In June 2020, Refracon completed the repair of blast furnace stack No. 6 of Nizhniy Tagil Metallurgical Plant. The intervention was completed with monolithic refractory materials installed by shotcreting.
24 September 2020